Unit 3 Assignment 2 – Planning for EHR
- Due Sunday by 11:59pm
- Points 40
- Submitting a text entry box, a website url, a media recording, or a file upload
Instructions
- Review the information provided for an example EHR implementation, including each activity’s duration and predecessor(s):
Activity | Duration (days) | Predecessor | |
A | Create the EHR vision | 5 | – |
B | Identify the planning horizon | 10 | A |
C | Obtain buy-in from affected parties | 30 | B |
D | Develop a financing and acquisition strategy | 10 | C |
E | Develop functional, data, and technical strategies | 45 | C |
F | Conduct vendor selection | 45 | D, E |
G | Plan the EHR implementation | 15 | C, E, F |
H | Conduct benefits realization study | 10 | A-H |
- Draw the PERT or GANTT chart for this implementation based on the information provided.
- Indicate the critical path on the PERT or GANTT chart.
- Your file should be in Microsoft Word, Microsoft PowerPoint, Microsoft Excel, or Adobe Acrobat format.
- Cite all sources in APA format.
- Submit your PERT or GANTT chart for grading.
- Reminder: You must upload your completed document using Browse My Computer. Then, hit the Submit button to successfully complete the assignment submission process. Do not copy and paste text into the text box.
Rubric
Unit 3 Assignment 2 – Planning for EHR
Criteria | Ratings | Pts | ||||||
---|---|---|---|---|---|---|---|---|
This criterion is linked to a Learning OutcomeContent |
| 20.0 pts | ||||||
This criterion is linked to a Learning OutcomeAnalysisPRICE-P |
| 10.0 pts | ||||||
This criterion is linked to a Learning OutcomeWriting |
| 5.0 pts | ||||||
This criterion is linked to a Learning OutcomeAPAPRICE-I |
| 5.0 pts | ||||||
Total Points: 40.0 |
Unit 3 Assignment 1 – ONC” aria-describedby=”msf0-previous-desc”>PreviousNext
Expert Solution Preview
Introduction: In this assignment, we are presented with an example EHR implementation plan and asked to draw a PERT or GANTT chart based on the provided information. We are also asked to indicate the critical path on the chart and submit it in APA format.
Answer:
Activity Duration (days) Predecessor
A Create the EHR vision 5 –
B Identify the planning horizon 10 A
C Obtain buy-in from affected parties 30 B
D Develop a financing and acquisition strategy 10 C
E Develop functional, data, and technical strategies 45 C, F
F Conduct vendor selection 45 D, E
G Plan the EHR implementation 15 C, E, F
H Conduct benefits realization study 10 A, G
Based on the provided information, the PERT chart would look something like this:
[Insert image of PERT chart]
The critical path, which is the longest duration path through the diagram, is A-C-F-E-G-H with a total duration of 150 days. Any delay in this critical path will delay the entire project.